Logie Building Services Ltd.

Andover Primary School

Client Angus Council
Location Andover Primary School, Brechin
Scope Of Work Internal/External Alterations
Schedule 7 Weeks

Project Detail

Client: – Angus Council
Value: – £170,000
Duration: – 7 weeks

Activity Space
Formation of a new activity space through the removal of existing boys and girls toilets. This area was then redesigned to create an open space including the fitting of kitchen units and sinks.

pic2 pic1

Toilet
To accommodate for the removal of the existing toilet facilities, new toilets and a nappy change area were created by the use of IPS panels and Toilet cubicle systems.

pic3a

Snack/Kitchen Area
Stud partitioning was erected to form a new snack area. This included fitting kitchen unit’s etc. at varying heights to accommodate the needs of adults and children.

pic4

Storage
Existing spaces within the school were utilised to create a storage area to compensate for the storage space which was lost due to other works. The new storage area was fitted with a laminated spur lock shelving system to give maximum storage space.

pic5

Doors & Ironmongerynew oak finished fire rated door sets and ironmongery were fitted throughout the school to create fire compartments throughout the school to offer protection to the remainder of the building.

pic6doora

New Entrance
A slap was carried out through an existing external wall in order to form an opening. An aluminium door was fitted, along with an aluminium screen and window. A level slab area was created to make the door fully accessible.

pic7

Sensory Room
A new room was installed with sensory equipment included to specialised equipment designed to create an environment that is used for relaxation and calming.

pic8

Accessible Toilet
An accessible toilet was created in accordance with the Disability Discrimination Act Regulations.

pic9a

Learning Space
A learning space was created for pupils with additional support needs, with the provision of kitchen equipment.

pic11a

New Suspended Ceilings were installed where required and altered to accommodate for the removal of existing walls. Vinyl and carpet were laid throughout areas where works were carried out. Areas within the school also received an electrical re-wire. Re-routing of existing pipework was also carried out to accommodate all the new works to WRAS standards. Heating facilities were altered as required throughout the works, as well as the fire and intruder alarms to take new areas into account.

pic12 pic14 pic13